How do I track EOT claims and delay notices?

Keep an EOT register that links each delay event to the programme activity it affects, the notice issued, its deadline and the evidence: site diary entries, photos and correspondence. Hivenox keeps that register on the same record as the programme and site diaries, so evidence is attached as it is captured.

  • By Hivenox
  • Last reviewed
  • 3 min read
Two site engineers reviewing drawings on a building site
For project managers, site managers and contract administrators on head contracts and subcontracts.
On this page
  1. What goes in an EOT register
  2. Step by step
  3. Records to keep
  4. Common mistakes
  5. How Hivenox handles it

What goes in an EOT register

An EOT claim is only as strong as its evidence and its timing. Most contracts require notice of a delay within a set period, then a claim with the details. Miss either, and the entitlement can be lost.

Keep one register per job, with one row per delay event, updated as the job runs.

The columns of an EOT register
ColumnWhat to record
Delay eventWhat happened, when it started and what caused it
Programme activityThe activities it affects, and whether they're on the critical path
NoticeThe notice issued, the clause it relies on and the date it was sent
DeadlineThe time-bar for the notice and for the claim
EvidenceSite diary entries, photos, correspondence, RFIs and instructions
Days and statusDays claimed and granted; open, submitted, granted, rejected or disputed

Step by step

1

Record the delay the day it starts

Note the cause, the area affected and who is involved in the site diary, with dated photos.

2

Link it to the programme

Identify the activities it affects and whether they're on the critical path. Keep the programme updated so the impact can be shown.

3

Check the notice clause

Find the notice period and form in your contract. Head contract and subcontract periods often differ, so diarise both.

4

Give notice, then keep it current

Send the notice before the time-bar. For a continuing delay, send updates as the contract requires.

5

Build the claim

Show the cause, the effect on the critical path and the days claimed, with the evidence attached.

6

Track the decision

Record the days granted or rejected and the reasons, through to practical completion.

Records to keep

Site diary entries for every day of the delay
Dated photos of the affected area
The programme before and after the delay
Instructions, RFIs and correspondence about the cause
Weather records, where weather is the cause
The notice and the claim, with proof of when each was sent
The decision: days granted or rejected, and why

Common mistakes

Notice sent late, or not at all

A strong claim can still fail on a missed time-bar.

No link to the programme

If a delay can't be shown on the critical path, it's hard to claim time for it.

Diaries written up after the fact

Records made weeks later carry less weight. Record it on the day.

Head contract and subcontract out of step

Track both sets of notice periods, so a subcontractor's notice reaches you in time to notify the principal.

A register in one person's spreadsheet

It goes missing when people move on. Keep it on the job record.