What is a payment schedule under the NSW Security of Payment Act?

A payment schedule is the respondent's written reply to a payment claim, stating how much it will pay and why any amount is withheld. Under the NSW Act it must be served within 10 business days of the claim, or sooner if the contract says so. Check current legislation and advice for your contract.

  • By Hivenox
  • Last reviewed
  • 3 min read
Two people reviewing and signing contract documents at a table
For head contractors, subcontractors and principals who serve or answer payment claims in New South Wales.
On this page
  1. How payment claims and schedules work
  2. Step by step
  3. Records to keep
  4. Common mistakes
  5. How Hivenox handles it

How payment claims and schedules work

The Building and Construction Industry Security of Payment Act 1999 (NSW) gives people who carry out construction work, or supply related goods and services, under a construction contract a right to progress payments.

The claimant serves a payment claim. The respondent answers with a payment schedule. What the schedule says, and when it is served, shapes everything that follows.

Payment claim
The claimant's claim for a progress payment, identifying the work and the amount claimed.
Payment schedule
The respondent's written reply: the amount it proposes to pay and, if less than claimed, why.
Scheduled amount
The amount the respondent proposes to pay.
Business day
Not a Saturday, Sunday or public holiday. Under the NSW Act, 27 to 31 December don't count either.
Adjudication
A fast statutory process for deciding a disputed payment claim.

Step by step

1

Log the claim the day it arrives

Record when and how it was served. Your deadline is the time in your contract or 10 business days, whichever is earlier.

2

Assess it against the contract

Check the work claimed against the contract, approved variations, rates, previous payments and retention.

3

Check the evidence

Use site diaries, photos, measurements, delivery dockets and inspection records for the work claimed.

4

Write the schedule

Identify the claim it answers and state the scheduled amount. For every amount withheld, give the reason, item by item.

5

Serve it on time, and keep proof

Serve it in a way the contract and the Act allow, and record when and how.

6

Pay what you scheduled

Pay the scheduled amount by the due date for payment.

Records to keep

The payment claim, with the date and method it was served
The contract and the approved variations
Your assessment: quantities, rates and calculations
Site diaries, photos and inspection records for the work claimed
Previous claims, schedules, payments and retention held
The payment schedule, and proof of when it was served
Correspondence about disputed items

Common mistakes

Replying late

If no payment schedule is served in time, the respondent can become liable for the full claimed amount.

Vague reasons

Reasons left out of the schedule generally can't be raised later in adjudication. Be specific.

Counting calendar days

The Act counts business days, and your contract may set a shorter time.

An email that isn't a schedule

A reply that doesn't identify the claim and state an amount may not count as a payment schedule.

Ignoring a claim you think is invalid

Serve a schedule anyway, and give your reasons.